The Golovnaya hydropower station was first built during the Soviet era and was completed in 1964. The original machine has 240 megawatts and has been running for nearly 60 years. This project is a power generation guarantee hydropower station for the Tajikistan power grid. Our company has supplied 3 sets of 2×875kN two-way gantry cranes and other gantry crane equipment, 3 sets of 2×160t+2×160t chain hoists, as well as 30kN trash rake machines and 250t/30t overhead cranes for the equipment renovation project of the Tajikistan Golovnaya Hydropower Station. The project was designed, renovated, installed, guided and debugged by Hangzhou Jianghe Mechanical and Electrical Equipment Engineering Co., Ltd.
250t/30t overhead crane